![]() |
Developing a software application or any product requires time and measuring the total time required to complete a specified amount of work requires some metrics. In Agile Scrum development methodology, there are two key metrics namely Story Point and Velocity, used to estimate a piece of work and measure the total amount of work completed in a Sprint. Table of Content In this article let us discuss Story Points and Velocity in more detail. Story PointsDefinition: Agile Scrum recommends Story Point as a method to measure the effort needed for a task or user story, instead of traditional time-based metrics such as hours and days estimates. Explanation of Working: Story Points are relative units to estimate the effort required to complete a user story or task based on the amount of effort needed, complexity of the task, risk involved, and uncertainty. In Agile Scrum, there are several methods to calculate story points. Story points focus on complexity instead of exact duration to complete a task. Common Methods of Story Points
VelocityDefinition: Velocity is a metric used to measure the amount of work a development team can accomplish within a specific Sprint in Agile Scrum. Explanation of Working: Velocity is calculated by adding up the completed user stories within a Sprint. Velocity only considers all tasks that were completed and delivered and not any tasks that are in progress or incomplete. The only story points included in calculating Velocity are those user stories marked and accepted as ‘Done’ Example: If a scrum team completed tasks total of 80 story points in a single Sprint, then the Velocity for that Sprint is 80. Steps in Calculating Velocity
Uses of Velocity
Relationship between Story Points and VelocityBelow are the key aspects of Story Points and Velocity as both are part of an Agile Scrum Development methodology:
Velocity is also a key metric for future Sprint Planning and this can help to assess the team capacity and determine how much work they can commit for the upcoming Sprint. Story Point and Velocity are interlinked and complement each other. Advanced TechniquesThere are other Advanced Techniques to estimate story points as discussed below:
ConclusionIn this article, we have looked into the estimation techniques in Agile Scrum and how story points are used to estimate story points. We have also discussed Velocity, a method to assess the amount of work completed in a Sprint. Story Point and velocity work hand-in-hand and together they form the crucial part of Agile project management. FAQs1. How to use story points to estimate velocity?Story Points are assigned to user stories using estimation techniques. At the end of a Sprint, add up all the story points which are completed. The sum of all story points is the Velocity of the current Sprint. 2. How can velocity be improved?The Velocity of a Scrum team can be improved by identifying and removing the factors that slow down team output and efficiency such as incomplete requirements, technical debt, and too many interruptions or bottlenecks. During the retrospective meeting, the team should reflect on its strengths and weaknesses and take actions for improvement. Also, the scrum team should improve their technical and communication skills for better performance. 3. How is velocity calculated?The sum of all story points completed in a Sprint is the Velocity of the current Sprint. Average velocity can be calculated by adding up the story points of 3- 4 completed sprints and dividing it by the number of sprints. Velocity can also be displayed on a chart with story points completed in each sprint, over time. 4. Do story points work better than time estimates?Story Points are given to each user story based on the effort, complexity, and risk involved in completing the user story or task. Time estimation is based on the hours required to complete a user story by analyzing the units of work to be completed. But both story point and time estimation have their advantages. The best estimation method depends on project needs, goals, and team preference. |
Reffered: https://www.geeksforgeeks.org
Geeks Premier League |
Related |
---|
![]() |
![]() |
![]() |
![]() |
![]() |
Type: | Geek |
Category: | Coding |
Sub Category: | Tutorial |
Uploaded by: | Admin |
Views: | 18 |